Spain – The mistake will cost £9million over three years to rectify


25 sailors and 7 officers and a spanish seal team. At 220+ feet long that must be palatial. Slower than crap but palatial.

Submarine Diary

Spain’s £1.75billion submarine programme is torpedoed after realising near-complete vessel is 70 tonnes too heavy because engineer put decimal point in the wrong place

  • Experts fear that the Isaac Peral will not surface again if sent to sea
  • The mistake will cost £9million over three years to rectify
  • A US company is to present a range of options to Spanish officials
  • The project could be set back two years by the error

 

A £1.75 billion Spanish submarine project has run aground after officials realised that the vessel is more than 70 tonnes too heavy – because an engineer put a decimal point in the wrong place.

A former Spanish official has described the mistake, which has led to fears that the submarine might not resurface if sent to sea, as ‘fatal’.

The Isaac Peral, the first in a new class of diesel electric submarines, was almost complete when the…

View original post 547 more words

Advertisements

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Google+ photo

You are commenting using your Google+ account. Log Out / Change )

Connecting to %s

Categories

%d bloggers like this: